Construction of the US-82 Gordo Bypass began in October of 2024; it is expected to open ahead of schedule at the end of the month. However, the Pickens County Sheriff's Office says motorist are already attempting to use the roadway and that is not a safe proposition right now.

The Alabama Department of Transportation (ALDOT) warns that workers and equipment are still present on the eight-mile stretch of highway from the northwest city limits of Gordo to just east of the Tuscaloosa County line.

Tuscaloosa Thread logo
Get our free mobile app

In a Facebook post, the sheriff's office advised motorists to have patience,

"Construction crews are working hard to complete the project, and it is expected to partially open by the end of July if everything stays on schedule. Unfortunately, individuals who choose to drive on the bypass before it officially opens are creating safety hazards for the workers and delaying the completion of the project.

"For the safety of everyone involved and to help ensure the project is completed as quickly as possible, we ask that everyone please refrain from using the Gordo Bypass until it is officially opened to the public."
The $45.5 million project was awarded to S.T. Bunn Construction Company and is expected to improve safety, mobility and commerce in West Alabama according to ALDOT.
The is costing the state an additional $1.76 million because a required newspaper notice of bids being let was not properly made. ALDOT notes the bypass is under budget. The overall cost of the realignment is an 80% federal, 20% state split.
The current US-82 through Gordo will remain open and will be maintained by the state.